| GPRA Goal/Annual Target | SC GG 3.1/23.1 Implement a field-oriented, integrated experimental research program to quantify coupled processes that control reactive transport of at least one key DOE contaminant. |
| 1st Quarter Measures | Announce at least one award from solicitation 06-16 for a field research effort targeting coupled processes with application to at least one key DOE contaminant |
| 1st Quarter Results | January 8, 2007 ERSD (now CESD) funds three field sites for subsurface contaminant transport research: BER's Environmental Remediation Sciences Division (ERSD (now CESD)) has established three large field sites for conducting subsurface research on the fate and transport of DOE contaminants. These five year, $3M/year awards will fund multi-disciplinary teams of scientists working at DOE sites to make significant advances in the conceptual understanding and computational simulation of subsurface processes affecting contaminant transport at the field scale. These sites also will provide samples and site access to scientists within ERSD (now CESD) programs to further test small scale, laboratory-derived hypotheses at larger scales in the field under environmentally relevant conditions. The three sites are located on the Oak Ridge Reservation, at the Hanford 300 Area, and at a uranium mill tailings site in Rifle, Colorado. Lead PIs for these projects were asked to coordinate with the local EM or LM offices to align basic science needs in support of subsurface cleanup and/or long term stewardship decisions with the science goals of the project. |
| 2nd Quarter Measures | March 30, 2007 Implementation Plan for the Integrated Field-Scale Challenge (IFRC) project at the Oak Ridge Field Research Center (ORFRC) Oak Ridge, Tennessee |
| 2nd Quarter Results | Click here for results (pdf) |
| 3rd Quarter Measures | Site visit by ERSD (now CESD) program manager to project. |
| 3rd Quarter Results | From: Bayer, Paul Dear Dr. Kuperberg, |
| 4th Quarter Measures | Year 1 Implementation Plan progress report delivered from project. |
| 4th Quarter Results | 4th Quarter Measures September 30, 2007 Implementation Plan progress report for the Integrated Field-Scale Challenge (IFRC) project at the Oak Ridge Field Research Center (ORFRC) Oak Ridge, Tennessee Click here for results (pdf) |
| Weight | 20% |